According to Government, the coronavirus pandemic cannot stop the ‘Year of Roads’ agenda.
Finance Minister, Ken Ofori-Atta, made this known on Thursday, July 23, 2020.
He was presenting the 2020 Mid-Year Budget Review.
He stated that the Pokuase Interchange project was 74 percent complete.
Also, he said the Tema Motorway Roundabout has been completed, and that the Obetsebi-Lamptey Circle Interchange was 45 percent complete.
He added that the Kumasi Lake Roads and Drainage extension project was 55 percent complete.