The Volta River Authority (VRA), GRIDCo and Electricity Company of Ghana (ECG) have assured that there will be enough power supply as they shut down Ghana National Gas Company (GNGC) for maintenance. Management reveals that the shut down is to facilitate the connection and commissioning of the gas pipeline system and other equipment from TEN fields to Atuabo processing plant […]
The post No ‘Dumsor’ as Ghana Gas Shuts Down -ECG, others assure appeared first on Ultimate FM.
The Volta River Authority (VRA), GRIDCo and Electricity Company of Ghana (ECG) have assured that there will be enough power supply as they shut down Ghana National Gas Company (GNGC) for maintenance.
Management reveals that the shut down is to facilitate the connection and commissioning of the gas pipeline system and other equipment from TEN fields to Atuabo processing plant from February 3 – 20, 2017.
‘This anticipated shortfall of 230MW is creating public anxiety that the country may be returning to power crises (dumsor).
We wish to assure the public that we have put in adequate measures to mitigate the impact of the shortfall as detailed below: We plan to generate additional power from the Akosombo and Kpong hydroelectric plants, and also from the Tema and Kpone thermal plants which operate on light crude oil (LCO) and diesel respectively, while imports from Cote d’Ivoire will be purchased to make up for the supply deficit,’ the regulators in a joint statement said.
Read details of the statement:
JOINT PRESS RELEASE VRA, GRIDCo and ECG For Immediate Release
POWER SUPPLY ARRANGEMENT – FEBRUARY 2017
Following the announcement of a planned shut down by the Ghana National Gas Company (GNGC) for maintenance and also to allow for the connection and commissioning of the gas pipeline system and other equipment from the TEN fields to the Atuabo processing plant from 3rd to 20th February, 2017, we wish to advise that there will be a generation shortfall of 230MW from the AMERI plant whose operations depend solely on gas supply from the GNGC.
The connection of the TEN fields to the Atuabo plant is critical as it will significantly increase the amount of natural gas to run the power generating facilities at Aboadze and improve the overall reliability of power supply to the general public. This anticipated shortfall of 230MW is creating public anxiety that the country may be returning to power crises (dumsor).
We wish to assure the public that we have put in adequate measures to mitigate the impact of the shortfall as detailed below: We plan to generate additional power from the Akosombo and Kpong hydroelectric plants, and also from the Tema and Kpone thermal plants which operate on light crude oil (LCO) and diesel respectively, while imports from Cote d’Ivoire will be purchased to make up for the supply deficit. Additionally, some of the thermal units at Aboadze that have been shut down for planned maintenance would be returned into service during this period.
We take this opportunity to assure electricity consumers and the general public that the power situation will be managed in the most efficient manner during this period to address the anticipated challenges in power supply.
We thank our valued customers for their understanding and cooperation.
Date/Venue: January 23, 2017/Accra.
Jointly Issued by: Volta River Authority, Ghana Grid Company Ltd. and Electricity Company of Ghana TO:
By: Ghana/Ultimatefmonline.com/106.9FM
The post No ‘Dumsor’ as Ghana Gas Shuts Down -ECG, others assure appeared first on Ultimate FM.
Read Full Story